The short answer
- From signing to switching on often takes one to three months: design, permit, install, inspection, then the utility's permission to operate (PTO).
- The utility step is the shortest for simple systems: SCE says simple solar-only applications may get PTO within 10 business days, and SDG&E says PTO "usually takes up to five business days".
- Batteries, panel upgrades and HOA approval add time.
- Don't turn the system on before PTO.
The steps
- Site visit and design (1–2 weeks).
- HOA approval if needed (up to 45 days by law; HOA rules).
- Permit: instant in SolarAPP+ cities, days to weeks elsewhere (permits).
- Installation: usually 1–3 days.
- City inspection.
- Utility interconnection and permission to operate.
How long utility approval took in 2025
Days from the utility receiving the interconnection application to permission to operate, home solar systems:
| County | Median | Middle half | Systems |
|---|---|---|---|
| Los Angeles County | 33 days | 6 days – 90 days | 15,082 |
| Orange County | 35 days | 7 days – 80 days | 7,852 |
| San Diego County | 25 days | 7 days – 61 days | 11,273 |
| Riverside County | 29 days | 7 days – 85 days | 13,592 |
| San Bernardino County | 24 days | 6 days – 72 days | 10,426 |
| Ventura County | 42 days | 11 days – 80 days | 3,306 |
By utility: SCE 30 days, SDG&E 26 days (medians).
Our figures: California DG Stats interconnection records for SCE and SDG&E homes, through Aug 31, 2026. How we count.
Speeding it up
- Choose an installer that files complete applications (ask how long their recent jobs took).
- Sign the CPUC consumer protection guide promptly; SCE and SDG&E won't connect without it.
- Have your utility account number and a recent bill ready.
Checked against official sources on Oct 1, 2026. Sources are linked in the text. Not legal, tax or financial advice.