The short answer

The steps

  1. Site visit and design (1–2 weeks).
  2. HOA approval if needed (up to 45 days by law; HOA rules).
  3. Permit: instant in SolarAPP+ cities, days to weeks elsewhere (permits).
  4. Installation: usually 1–3 days.
  5. City inspection.
  6. Utility interconnection and permission to operate.

How long utility approval took in 2025

Days from the utility receiving the interconnection application to permission to operate, home solar systems:

CountyMedianMiddle halfSystems
Los Angeles County33 days6 days – 90 days15,082
Orange County35 days7 days – 80 days7,852
San Diego County25 days7 days – 61 days11,273
Riverside County29 days7 days – 85 days13,592
San Bernardino County24 days6 days – 72 days10,426
Ventura County42 days11 days – 80 days3,306

By utility: SCE 30 days, SDG&E 26 days (medians).

Our figures: California DG Stats interconnection records for SCE and SDG&E homes, through Aug 31, 2026. How we count.

Speeding it up

Checked against official sources on Oct 1, 2026. Sources are linked in the text. Not legal, tax or financial advice.