In short
- Glendale nets what you use against what you send to the grid in each billing period, so exports offset your purchases at retail value.
- Since Nov 1, 2023, systems up to 10 kW are exempt from the cap of 110% of past use and may add up to 30 kWh of storage without a storage meter.
- GWP no longer offers solar incentives, and we found no battery rebate.
Rebates and incentives
None found (Oct 1, 2026).
Getting connected
Under 15 kW: apply in PowerClerk, GWP review in 3–5 business days, Glendale building permit, install and inspection, then meter reprogramming (7–10 working days) before permission to operate. [email protected], 818-548-2750.
Cities served
Also: Glendale.
Sources
Checked at each utility's own pages on Oct 1, 2026. Rules and rebates change: confirm with the utility before you sign a contract.