In short

Rebates and incentives

No general LADWP solar or battery rebate (Oct 1, 2026). Low-income homes can join the SGIP equity waitlist ([email protected]).

Getting connected

Your installer applies on LADWP's Solar Automated Meter Spot site (ladwp.com/nem) and pulls an LADBS permit. Inspections by LADBS and LADWP come before the net meter is installed. Systems under 10 kW AC without a battery may get a fast track. LADWP doesn't publish a timeline.

LADWP home solar by year

From City of Los Angeles building permits (LADBS), issued through Sep 27, 2026.

YearSolar permitsWith a batteryBattery shareBattery-only permits
2026 (through Sep 27)2,64461023%346
20254,06391823%479
20243,21771822%403
20234,94382817%406
20224,77683918%276
20214,6641,20826%392
20202,79464023%319

Cities served

Sources

Checked at each utility's own pages on Oct 1, 2026. Rules and rebates change: confirm with the utility before you sign a contract.